TCEQ has assessed the City of Tolar a $68,687 wastewater penalty and conditionally offset the entire amount if the city completes a $2.64 million plant upgrade.
A 2024 record review found effluent-limit violations at the city's plant on Tolar Cemetery Road from August 2023 through July 2024, plus a missed E. coli sample in April 2024. Among the readings in the order: a single-grab E. coli result of 2,420 colony-forming units per 100 milliliters in August 2023, against a limit of 399, and a single-grab total suspended solids result of about 1,634 milligrams per liter in May 2024, against a limit of 60.
Mayor Matt Hutsell signed the agreement July 16. Commissioners signed the order Nov. 10, which starts the clock. Tolar must begin a sequencing batch reactor upgrade within 30 days and finish it within 130 days, and must certify permit compliance by March 20, 2027. If the work is not completed as required, TCEQ can demand payment of the penalty.
The documents are a TCEQ public record (Docket No. 2025-0070-MWD-E). Hood County Express has asked the city for comment and will update this story with any response.
Hood County Express — Est’d 1/26 🚂
https://www.facebook.com/share/1Dsz4kJYVp/?mibextid=wwXIfr
HoodCountyExpress.com
#HoodCounty #GranburyTX #Tolar #TCEQ #TexasNews #News #USNews